Road News - October 16 update

Continued paving of Richards Road and ground preparation of the Ghost Transfer site is scheduled to start Thursday, October 17, 2019. During the paving operations on Richards road, expect minor delays. 

Due to the site preparation of the Ghost River Transfer Station access into the site may be by foot traffic only, thus it is recommended that residents requiring use of the site only take a minimal amount on garbage/recyclables on Saturday, October 19, 2019, paving of the site itself is anticipated to be completed during the week of October 21 – 25, 2019 and relocation of the bins shortly thereafter.

_________________________________________________________________________________________________________________________________________________________ 

2019 Pavement rehabilitation program and paver patching is planned to start Monday, October 14.

Work will include:

  • Ground Preparation and paving of the Ghost River Transfer Station and access road.
  • Continued shoulder prep. and paving of 2.6 km. of Richards Road.
  • Paver Patching on Jamieson Road.

Bow Corridor snow maintenance

Volker Stevin Highways Limited (VSHL) will have a new operator for snow maintenance in the Bow Corridor this winter.  Please bear with us during this time of transition as snow maintenance of the Bow corridor hamlets is very complex and challenging.